FOURTH OF JULY CREEK

Bridges

Project Profile

Location  Near Salmon, ID (Lemhi County)
Size 14’ X 30’
Scope Precast Concrete SuperSill ™ Abutment System

TrueNorth Steel engineered and fabricated this modular steel bridge for a private land owner. This bridge was made with a pre-engineered, precast, concrete SuperSill™ abutement system, which led to easy installation and no need for a crane. One unique aspect of this project is that the replacement of pipe led to impoved salmon migration. Additionally, the installation process was simple with bolt-together installation, which helped reduce project costs.